To ask the Secretary of State for Energy Security and Net Zero, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Great British Energy, by when does she plan to open the Aberdeen headquarters.
To ask the Secretary of State for Energy Security and Net Zero, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Great British Energy, by when does she plan to open the Aberdeen headquarters.
Great British Energy (GBE)'s headquarters is in the Marischal Square development in Aberdeen city centre.
The headquarters opened on 1 September 2026, with full staff occupation taking place from week commencing 7 September.
To ask the Secretary of State for Energy Security and Net Zero, what level of capital funding has been (a) allocated and (b) awarded by GB Energy for nuclear power projects.
To ask the Secretary of State for Energy Security and Net Zero, what level of capital funding has been (a) allocated and (b) awarded by GB Energy for nuclear power projects.
Great British Energy and Great British Energy Nuclear (GBE-N) operate as two separate and allied publicly owned companies with a shared mission to accelerate the deployment of clean energy assets.
The GBE-N small modular reactor programme was allocated £2.6 billion at the 2025 Spending Review.
This funding is being used by GBE-N to progress the Gwyndod project on Anglesey in North Wales, including design activities under the Technology Partner contract signed with Rolls-Royce SMR. The total value of contracts awarded by GBE-N has now reached nearly £900m.
To ask the Secretary of State for Energy Security and Net Zero, what the staffing numbers are for Great British Energy; how many staff are (a) directly employed, (b) contractors and (c) secondees; from which (i) department, (ii) agency, (iii) public body and (iv) other organisation they have been seconded;...
To ask the Secretary of State for Energy Security and Net Zero, what the staffing numbers are for Great British Energy; how many staff are (a) directly employed, (b) contractors and (c) secondees; from which (i) department, (ii) agency, (iii) public body and (iv) other organisation they have been seconded;...
Great British Energy (GBE) has a total headcount of 132: (a) 55 directly employed (permanent) staff, (b) 31 contractors, and (c) 46 secondees. Secondees are based 2 in Aberdeen, 10 elsewhere in Scotland, and 34 in the rest of the UK. The majority of secondees have joined from the Department for Energy Security and Net Zero (the majority) and others are drawn from the Scottish Government, Ofgem, the Government Legal Service, the Department for Education, ORE Catapult, Baringa, CO2 Sense and Xodus Group. A full list of secondee roles and durations is attached.
To ask the Secretary of State for Energy Security and Net Zero, what estimate she has made of the number of jobs expected to be created in Ayrshire or the West of Scotland through GB Energy investments.
To ask the Secretary of State for Energy Security and Net Zero, what estimate she has made of the number of jobs expected to be created in Ayrshire or the West of Scotland through GB Energy investments.
The Government has not made a specific estimate of the number of jobs expected in Ayrshire or the West of Scotland. Great British Energy (GBE) invests on a UK-wide basis, and its investment decisions and job impacts cannot be predicted by region at this early stage. GBE's Strategic Plan commits it to supporting at least 10,000 jobs by 2030 nationwide.
To ask the Secretary of State for Energy Security and Net Zero, how many direct roles have been created within GB Energy since its establishment.
To ask the Secretary of State for Energy Security and Net Zero, how many direct roles have been created within GB Energy since its establishment.
Great British Energy (GBE) is currently building its permanent workforce following its establishment. GBE has 132 people working for the organisation, which includes permanent GBE staff, individuals seconded to the organisation and contingent workers. Since GBE’s pay case was finalised in April, it has launched significant recruitment and is aiming to reach 200 FTE by April 2027 and 300 FTE by April 2028; with the majority of staff based in their Aberdeen HQ. Through its activities and investments, GBE will also support thousands of jobs across the UK.
To ask the Secretary of State for Energy Security and Net Zero, what proportion of GB Energy staff live outside Scotland; and how many days a week the staff must be in the office in Scotland.
To ask the Secretary of State for Energy Security and Net Zero, what proportion of GB Energy staff live outside Scotland; and how many days a week the staff must be in the office in Scotland.
The Government does not keep records of Great British Energy (GBE) staff home addresses. GBE does not set a fixed number of office days, instead agreeing working arrangements individually and supporting hybrid working where appropriate, though this may not suit all roles or teams. As an operationally independent company, it is for GBE to set its own working policies.
To ask the Secretary of State for Energy Security and Net Zero, what level of capital funding has been (a) allocated and (b) awarded by GB Energy for solar energy firms in England.
To ask the Secretary of State for Energy Security and Net Zero, what level of capital funding has been (a) allocated and (b) awarded by GB Energy for solar energy firms in England.
Great British Energy (GBE) does not allocate or publish capital funding by technology or by nation; it is operationally independent and takes investment decisions based on individual opportunities and value for money. GBE has awarded solar funding in England through its £7.5 million investment in Naked Energy, a UK firm whose solar-thermal technology is deployed at sites including the British Library and Wimbledon, and which will fund a new UK manufacturing facility. Government and GBE have also separately invested up to £300m to date for solar installations across hundreds of schools and hospitals in England, as well as multiple military sites. GBE also funded schemes in Scotland, Wales and Northern Ireland. The Devolved Governments could choose between funding public sector renewables schemes and community energy projects.
To ask the Secretary of State for Energy Security and Net Zero, how many jobs have been created as a direct result of investment decisions taken by GB Energy.
To ask the Secretary of State for Energy Security and Net Zero, how many jobs have been created as a direct result of investment decisions taken by GB Energy.
Since its establishment, GB Energy’s investments have supported approximately 1,500 jobs nationwide. As GBE increases its activity in the renewable energy market, we can expect this to rise in line with its targets to support over 10,000 jobs by 2030.
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what estimate he has made of the number of jobs that could be supported by new nuclear developments...
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what estimate he has made of the number of jobs that could be supported by new nuclear developments...
GBE N's study of Scotland's potential for new nuclear indicates that it has land areas with high potential for future development.
New nuclear projects can deliver billions of pounds of investment and thousands of high-quality jobs to a region. While the Scottish Government currently opposes new nuclear power stations, UK Ministers remain open to discussions regarding opportunities for new nuclear in Scotland.
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what assessment he has made of the potential generating capacity that could be delivered if new nuclear power...
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what assessment he has made of the potential generating capacity that could be delivered if new nuclear power...
GBE N's study of Scotland's potential for new nuclear identified potential land areas rather than specific sites, and does not make an assessment of potential generating capacity.
However, the report indicates that Scotland has land areas with high potential for future development and UK Ministers remain open to discussions regarding opportunities for new nuclear in Scotland.
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what discussions he has had with the Scottish Government on the report's findings.
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what discussions he has had with the Scottish Government on the report's findings.
Ministers commissioned GBE N's study of Scotland's potential for new nuclear last autumn.
The study indicates that Scotland has land areas with high potential for future development.
We remain open to discussions with the Scottish Government regarding opportunities for new nuclear in Scotland.
To ask the Secretary of State for Energy Security and Net Zero, whether his Department plans to support further assessment of Dounreay as a site for future nuclear deployment following the publication of Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report.
To ask the Secretary of State for Energy Security and Net Zero, whether his Department plans to support further assessment of Dounreay as a site for future nuclear deployment following the publication of Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report.
Great British Energy – Nuclear's assessment concluded that parts of Scotland, including areas around Dounreay, have technical potential for future new nuclear development. However, planning policy is devolved to the Scottish Government. Their current policy does not enable the building of new nuclear power stations in Scotland.
New nuclear projects can deliver billions of pounds of investment and thousands of high-quality jobs, and UK Ministers remain open to discussions with the Scottish Government regarding opportunities to deploy new nuclear technologies in Scotland.
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what discussions he has had with the Scottish Government on supporting the potential development of new nuclear at...
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what discussions he has had with the Scottish Government on supporting the potential development of new nuclear at...
Ministers commissioned GBE N's study of Scotland's potential for new nuclear last autumn.
The study indicates that Scotland has land areas with high potential for future development. We remain open to discussions with the Scottish Government regarding opportunities for new nuclear in Scotland.
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what assessment he has made of the potential impact of new nuclear development at Dounreay on the economy...
To ask the Secretary of State for Energy Security and Net Zero, with reference to Great British Energy – Nuclear's Technical Advice on Potential Future Nuclear Power Plant Siting in Scotland report, what assessment he has made of the potential impact of new nuclear development at Dounreay on the economy...
GBE N's study of Scotland's potential for new nuclear indicates that it has land areas with high potential for future development.
New nuclear projects can deliver billions of pounds of investment and thousands of high-quality jobs to a region.
While Scottish Government policy currently does not enable new nuclear power stations in Scotland, UK Ministers remain open to discussions regarding opportunities for new nuclear in Scotland.
To ask the Secretary of State for Energy Security and Net Zero, with reference to the direct ministerial appointments gov.uk portal entry of 20 April, Interim Non-Executive Director Great British Energy and Great British Energy Start-Up Chair, for what reason the five non-executive directors and chairman to Great British Energy...
To ask the Secretary of State for Energy Security and Net Zero, with reference to the direct ministerial appointments gov.uk portal entry of 20 April, Interim Non-Executive Director Great British Energy and Great British Energy Start-Up Chair, for what reason the five non-executive directors and chairman to Great British Energy...
The start-up Chair and five Non-Executive Directors of Great British Energy (GBE) were appointed through direct ministerial appointment to provide the expertise and experience needed for the rapid establishment of the company during its set-up phase.
Consideration will be given as to whether these positions should be regulated public appointments when the Public Appointments Order in Council is next updated. We are now running an open and fair competition for the permanent GBE board and all future GBE appointments will follow the process and principles of regulated public appointments.
To ask His Majesty's Government what progress Great British Energy has made in implementing its statutory object that slavery and human trafficking are not taking place in its supply chains; and what assessment they have made of the Politico investigation revealing that five out of seven of the contracts that...
To ask His Majesty's Government what progress Great British Energy has made in implementing its statutory object that slavery and human trafficking are not taking place in its supply chains; and what assessment they have made of the Politico investigation revealing that five out of seven of the contracts that...
There is no place for forced labour or unethical practices in the UK’s energy transition and Great British Energy (GBE) is expected to be a leading example of adherence to the UK’s legislation and longstanding position on forced labour.
Solar panel supply chains are complex, and it is extremely difficult to confirm the exact origins of their multiple components and raw materials which make up a solar panel.
All contracts issued under the GBE schools and hospitals solar initiative complied with UK Procurement Act 2023, including extensive requirements on participants of Government’s frameworks to comply with the Modern Slavery Act.
GBE continues to go further to tackle forced labour and is currently formalising its independent requirements of partners. It will set out further detail over the coming months. In addition to conducting risk-based due diligence in line with international human rights standards, GBE is also exploring other measures, including ways to reward companies that demonstrate robust performance in this area. This approach is already reflected in the scoring criteria for its £300 million Offshore Wind and Networks Grant Fund.