If Sec of State for Wales will invite tenders in 1990 to enable sections on M4 between Lon Las & Baglan to be completed by end of 1992.
Asked by
Gareth Wardell (Labour)
Answering body
Welsh Office
Oral questions - Lead
Status
Answered
Date
6 November 1989
Reference
159 c665
House
House of Commons
Answered by
Lord Roberts of Conwy (Conservative)
Answering body
Welsh Office
Type
Oral answers to questions
Date
6 November 1989
Reference
159 c665
House
House of Commons
1st supplementary on effect of incomplete M4 on employment & inward investment.
Asked by
Gareth Wardell (Labour)
Answering body
Welsh Office
Oral questions - 1st Supplementary
Status
Answered
Date
6 November 1989
Reference
159 c665
House
House of Commons
Answered by
Lord Roberts of Conwy (Conservative)
Answering body
Welsh Office
Type
Oral answers to questions
Date
6 November 1989
Reference
159 c665
House
House of Commons

Are there any plans to provide a new service area on M4 between Heston & Membury.

Asked by
Simon Coombs (Conservative)
Answering body
Department of Transport
Type
Written questions
Status
Answered
Date
25 October 1989
Reference
158 c503W
House
House of Commons

What is latest estimate of cost of constructing M4 link at Baglan; what is length of time that actual construction would take; & what is latest date at which a decision could be taken to start construction in April 1991. - (Holding answer 23 October 1989) - Includes table.

Asked by
Alan Williams (Labour)
Answering body
Welsh Office
Type
Written questions
Status
Answered
Date
24 October 1989
Reference
158 c379-80W
House
House of Commons

How much has been spent on safety fencing on M4 during year 1988-89; how much is expected to be spent in 1989-90; & of amounts spent or to be spent, how much is attributable to replacements of faulty safety fencing.

Asked by
Lord Clark of Kempston
Answering body
Department of Transport
Type
Written questions
Status
Answered
Date
6 July 1989
Reference
156 c254-5W;156 c256-7W
House
House of Commons

What action WO will be taking to minimise delays to traffic during construction of M4 between Baglan & Lonlas.

Asked by
Nicholas Bennett (Conservative)
Answering body
Welsh Office
Type
Written questions
Status
Answered
Date
25 April 1989
Reference
151 c467W;151 c465W
House
House of Commons

In view of the worsening of congestion along Baglan Road, Port Talbot, to accelerate the start of the work on the Baglan-Lonlas part of the M4.

Asked by
Lord Morris of Aberavon (Labour)
Answering body
Welsh Office
Type
Written questions
Status
Answered
Date
17 April 1989
Reference
151 c17-8W
House
House of Commons

When work commenced on the last part of the M4 to be completed; & why there has been a delay in the start of the Baglan-Lonlas Road.

Asked by
Lord Morris of Aberavon (Labour)
Answering body
Welsh Office
Type
Written questions
Status
Answered
Date
17 April 1989
Reference
151 c18W
House
House of Commons