If he will make a statement on the average time taken to complete major road schemes. - Includes figures from Highways Agency annual report. (Holding answer 10 February 1997).
If he will make a statement on the average time taken to complete major road schemes. - Includes figures from Highways Agency annual report. (Holding answer 10 February 1997).
Asked by
Jim Cunningham
(Labour)
Answered by
John Watts
(Conservative)
Answering body
Department of Transport
Type
Written questions
Status
Answered
For answer on
11 February 1997
Answered on
11 February 1997
Mr. Jim Cunningham: To ask the Secretary of State for Transport if he will make a statement on the average time taken to complete
major road schemes. [14572]
Mr. Watts: [holding answer 10 February 1997]:
Reducing the time taken to complete road schemes is an objective of the Highways Agency. Figures taken from the agency's annual
report for 1995-96 are given in the table. They show the average time taken, from programme entry to completion, for schemes
completed in each year.
1992-93: 15.0 years
1993-94: 11.9 years
1994-95: 11.4 years
1995-96: 13.4 years.
Of the 21 schemes analysed in 1995-96, five entered the programme over 20 years ago, one in 1969. If these schemes are taken out of
the analysis, the average time reduces to 10.6 years, showing a gradual fall over the four-year period.
Subjects
Construction; Administrative delays; Roads
Date
11 February 1997
Reference
14572; 290 c129W
House
House of Commons
What is the longest time recorded to complete a road scheme begun after 1979. - (Holding answer 10 February 1997).
What is the longest time recorded to complete a road scheme begun after 1979. - (Holding answer 10 February 1997).
Asked by
Jim Cunningham
(Labour)
Answered by
John Watts
(Conservative)
Answering body
Department of Transport
Type
Written questions
Status
Answered
For answer on
11 February 1997
Answered on
11 February 1997
Mr. Cunningham: To ask the Secretary of State for Transport what is the longest time recorded to complete a road scheme begun after
1979. [14573]
Mr. Watts: [holding answer 10 February 1997]: The longest time recorded to complete a road scheme begun after 1979 is 15 years. The
A65 Burley-in-Wharfdale bypass in west Yorkshire entered the programme in 1980 and was completed in 1995.
Subjects
Construction; Administrative delays; Roads
Date
11 February 1997
Reference
14573; 290 c129W
House
House of Commons