Written question asked by David Amess (Conservative) on Thursday, 8 December 2005, in the House of Commons. It was due for an answer on Monday, 12 December 2005. It was answered by Kim Howells (Labour) on Monday, 19 December 2005 on behalf of the Foreign and Commonwealth Office.
Building/Refurbishment Projects
- Question
- To ask the Secretary of State for Foreign and Commonwealth Affairs what (a) building and (b) refurbishment projects are planned by his Department in (i) 2005–06 and (ii) 2006–07; and what the expected costs are of each project.
- Answer
-
Building and refurbishment projects planned/being undertaken by the Foreign and Commonwealth Office in 2005–06 and 2006–07, and the expected costs of these projects in those years are:
£000 Building projects FY 2005–06 FY 2006–07 Algiers New offices 700 8,866 Almaty New offices 100 3,100 Amman New visa offices 820 400 Astana New offices 100 3,661 Baghdad New offices and staff accommodation 11,452 — Bangkok Staff accommodation 1,100 3,869 Bangkok Security work 600 — Basra New offices and staff accommodation 9,263 — Chennai New visa offices 1,170 10 Colombo New offices 500 5,600 Doha New offices and residence 1,105 4,410 Durban Office fit-out 159 — Dushanbe New offices and residence 764 5 Hanslope Park, Bucks Information and Communication Technology (ICT) Building 3,148 17,637 Hanslope Park, Bucks Childcare Nursery 250 500 Hanslope Park, Bucks Security work 500 500 Harare New offices 700 4,050 Islamabad/Karachi Staff accommodation 3,211 2,289 Istanbul New visa offices 100 2,900 Jakarta New offices 100 2,151 Kabul Office fit-out 200 273 Kabul Residence and staff housing 2,700 — Kampala New offices 1,500 — Ljubjlana Residence 100 1,116 Manila New offices 330 4,637 Mumbai New offices 250 1,332 Munich Office fit-out — 1,500 Pyongyang Office fit-out — 500 Rabat New offices 4,000 2,164 Sana'a New offices 4,000 2,773 Sarajevo New offices 200 600 Shanghai Office fit-out 40 — Skopje Office fit-out 3,500 — Tbilisi New offices 20 2,000 Tehran Staff accommodation — 2,000 Tirana Residence 1,263 20 Warsaw New offices 500 9,500 £000 Refurbishment projects FY 2005–06 FY 2006–07 Belgrade Health and Safety works 36 — Buenos Aires Security work 600 1,100 Buenos Aires Health and Safety works 2,700 163 Damascus Security works 775 — Dublin Security works — 1,800 King Charles St Fourth floor conversion to open plan 5,630 3,162 Kingston Health and Safety works 1,350 120 Manila Health and Safety works 468 400 Moscow Residence 301 4,010 Ottawa Offices 175 1,000 Tokyo Health and Safety works 290 1,150 Washington Offices 410 5
Secondary information
- Type
- Written question
- Reference
- 37416; 440 c2474-6W
- Session
- 2005-06
- Subjects
- Costs Construction Buildings Government departments Repairs and maintenance Foreign and Commonwealth Office
- Link
- View this Written question on www.publications.parliament.uk
Librarians' tools
- Timestamp
- 2013-11-24 21:06:08 +0000
- URI
- http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1094074
- In Indexing
- http://indexing.parliament.uk/Content/Edit/1?uri=http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1094074
- In Solr
- https://search.parliament.uk/claw/solr/?id=http://data.parliament.uk/pimsdata/Hansard/PARLIAMENTARY_QUESTION_1094074